Approval Timelines for Upcoming Conferences

 

Conferences Document to Physics group Group approval and Document to EB EB approval for col. review Full EB approval
Aspen
Jan 13 - 18, 2008
December 7, 2007 December 14, 2007 January 2, 2008 January 8, 2008
La Thuile
Feb 24 - Mar 1, 2008
January 22, 2008 January 29, 2008 February 12, 2008 February 19, 2008
Moriond EW
Mar 1 - 8, 2008
January 29, 2008 February 4, 2008 February 18, 2008 February 25, 2008
Moriond QCD
Mar 8 - 15, 2008
February 4, 2008 February 11, 2008 February 25, 2008 March 3, 2008

 

These timelines are based on the DØ approval procedure for analyses and a generic two-week EB review. For many analyses, EBs may need more than two weeks. It is in the best interest of physics groups and authors to get EBs involved and to get document to them early.

 

If a result is intended for conferences and publication, the collaboration review is two-week long. The above schedule will need to be moved ahead by one week in this case.

 