Reprocessing: Meeting of 14-Feb-2005: 9:30-10:30 ESNet video conference
Our meeting number on the ESNet is 823073776 (82d0repro).
Instructions to dial into a video conference via phone.
Agenda
- News
- Status of Merge Certification of Sites
- JIM Deployment and Remote Setup
- AOB.
Minutes
Participants
Jae Yu (SAR), Yann Cadou, Dugan O'Neil (Vancouver), Tibor Kruca (Lyon), Jörg Meyer, Lauren Duflot, Gabriele Garzoglio, Mike Diesburg, Daniel Wicke (FNAL)
Topics
- News
p17.03.00: Frozen, but
FPS calibration db server has problems in big production. DB access seems to be done for each channel indivitually and
thereby overloads DB server. This was ok in p17.02.00. A new release needs to be cut.
- Status of Merge Certification of Sites
- DØFarm: Plots produced for two of three datasets. Results don't agree. All differences in dataset...-2 could be attributed to problems in either RecoCert or MergeRecoCert, but new deviations observed in dataset..-1.
- WestGrid: Produced root tuples from unmerged files. Merging is ongoing.
- Lyon: Produced root tuples from unmerged files. Merging is ongoing.
- SAR: Certification datasets of unmerged files provided this morning.
- Wisconsin: Certification datasets in production.
- JIM Deployment and Remote Setup
- GridKa: Running properly last week. Monitoring is missing. Certification could be done.
- Wisconsin: Negotiating higher priority.
- Prague: Production jobs runs, but we have d0reco crashes (at a rate of 5-6%).
Reproducability and goodness of input files should be checked.
- UK: London: Firewall issues to be solved. Headnode, Sam-station and cluster are each separated by firewalls.
Manchester: Deployment ongoing at low priority.
- CMS Farm: --
- AOB:
Present RecoCert issues at conveenors meeting.
- Stuff discussed along the way:
Action Items:
Next Meeting
21-Feb-2005.
Mike Diesburg, Daniel Wicke, 3-Feb-2005. Last Change 14-Feb-2005.