D0Reco status: delay due to missing calibration data and the time needed for the following software certification. In addition it falls into the Christmas period. Most realisticly, reprocessing start will slip to the beginning of January Storage configuration: proposed 2 models of storage configuration were discussed (see http://www-d0.fnal.gov/computing/reprocessing/p20/docs/StorageTopology.txt) - input binary files cached at FNAL and also remotely in both models - input raw data are cached only at FNAL (1st model) or at FNAL as well as remotly (2nd model) - large scale test to be done with 1st model and eventual lessons to be learned Jobs submission: - centralized ? jim_client installed on d0mino or clued0 ? Andrew and Parag investigating/preparing this solution - our production team was asked to get/check their personal grid certificates - this week small tests of job submission to SAMGrid/OSG by all members of production team - not clear if we will be ready this week for large scale test with ~1000 jobs