P20 Reprocessing Should have no trouble getting adequate bandwidth from Enstore. Biggest problem will be bandwidth to remote sites. At this point don't believe we will need to stage at Lyon for LCG usage. Expect will have ~500 processors available. Ruth has been contacted regarding sites. We need to put together note describing needed resources and forward to OSG council. Tibor is working on this. Gabrielle is also working on estimates. Starting date has been moved to December 1st. Plan is to first do set for JES people. Need ~10% set with same lum profile as rest of data. Set has not yet been identified. Must have everything done by sometime in March, preferably the beginning of March. Should proceed with setting up sites with existing versions of reco. Jan Stark will be working on cal calibration. This is determining the December 1st start date.