= ACTION ITEM
BLS Systems
BLS PS: A second supply is under construction. This should
be ready by next week when DS is here to test with a full BLS crate in
the 5k. DS still has to add the trigger summers to the BLS cards
which put a load on the +13V line. There are 8 adders + 2 drivers
per board. These can be emulated with resistors.
The water cooling in the 5k needs to be fixed up to allow the test
supply to run. This is not of concern in the real detector as DS
claims there is plenty of flow available. We also have extra pipes
available to get separate cooling for the PS and the crates if need be.
Mike Cherry has pulled some of the pipes out that need rework and has
had the ends sweated off. We will replace these as we need them.
DH and DS believe we are still a couple of weeks away from being able
to sign off on the BLS transformer order. The order has been placed
and is waiting on us to say "Go!". We should probably check what
the lead time will be once we give the go-ahead.
PL has been modifying the monitor boards and writing up procedures.
He estimates about a day a piece which might get up to 1.5/day as one becomes
familiar with the procedure. He will check with Bob Jones group if
it is possible if they can do any of these (we have about 80 to do).
PULSER PS: No movement on these supplies as awaiting the control cable and connector.
ADC PS: The -5,2V rail in the ADC PS in the MCH for boxes 10 and 1 keeps tripping. This supply needs to pulled out and swapped which Mike Cherry and Victor Minor will do tomorrow. Also the supply for 11 and 0 occassionaly loses the +5V interlock which is fixed by a small modification that can be done in place. PL will look into these.
PL reported that the remaining monitor boards should be back from Chipco assembly at the end of March.
LG got the B3run system on the 3rd floor working again after DH added an extra #10 cable to the +5V line from the ADC supply. There was about a 0.1V drop on both the power and return line and the crate backplane was sitting at about 4.7-4.8V instead of 5.0V which made the Bit3 board very unhappy.
MG will continue testing stuffed preamp boards. All the CC boards are done and over 100 EC boards are done. Chipco had a delay in production after "losing" a reel of resistors but is now in production again and we expect shipments to start again next week. We have about 60-70 of the v3.1 motherboards which can be used in the meantime.
LG will test some of the Hx's in the test setup now that it is working again. We have received almost all the H's from MicroEngineering and are now in "spares" production as there originally delivered quantities fell short about 10%. We will also begin using these in board stuffing next week.
DS is concerned that he saw only about 5.3V full scale from the preamps on average during his tests last week. We had designed for closer to 6V for the full dynamic range (this was the original incentive for going to +12V on the output power rail). This means we only have about 0.3V of pile up before things become non-linear for large signals. DS is worried that the bias for the transistors is dependent on the temperature, which will make cooling the preamps more imperative. DS recalled that some measurements were taken by a Columbia summer student a few years ago (Abdrashitov?) and a D0 note was put out, which we need to try and relocate.
PP wondered about the tests with the grounding of the pulser command
cables that had been discussed at our previous meeting. DS did not
have time to do these last visit as is still not totally sure how the tests
were conducted in France. The grounding issues in the 5k test system
need to be resolved to finalize the tests.
DS also claimed that he saw a good ECL signal with the correct rise
time but it looked like there was 50 Ohm termination at the pulser fanout
end, instead of the required 75 Ohm to match the yellow command cables.
If this is the case, then about 1/2 the signal could be reflecting.
|
|
|
|
|
|
|
| 171 | 811 | 171 | 76 | 44.4 | 360 |
| 282A | 227 | 227 | 72 | 31.7 | 72 |
| 284 | 956 | ||||
| 285 | 1140 | ||||
| 317 | 1308 | ||||
| 318 | 824 | 824 | 526 | 63.8 | 526 |
| Total | 5266 | 1222 | 674 | 55.2** | 2904** |
From the previous productions and testing, this is what we have in hand:
| SCA type | Needed for 13 BLS systems (includes spares) | 4" | 6" | Total | Deficit |
| UP | 14976 | 7314 | 5232 | 12546 | 2430 |
| DOWN | 9984 | 6196 | 5223 | 11419 | 1435 spare |
| Total | 24960 | 13510 | 10455 | 23965 |