Note: Meeting time is now 10:00 am CDT on Fridays in DAB1.
Video connection available.
Contact Leslie Groer groer@fnal.gov.
= ACTION ITEM
Cables
The calorimeter pulser current cables have all
been cut and bundled (24 x 7), One bundle has been run to the NE
side (preamp box 11) - there is a problem closing the box with all the
cables in the back. We need to either find space for them so that
we can close the box or a possible solution is to make very short extender
rods (2-3 inches) to allow the boxes to stay open a small amount - the
time scale for this plus the need to remove and add rods with a box "hanging"
over the side makes this an unlikely solution. L. Bagby suggested
we strip the sheath and make sure we can get all the cable in the box and
close it, for at least one box.
The rest of the east side cables have been run
to the bottom of the cryostat. The cable tray for box 8 (SW side
of CC) has been cut away to make way for the solnoid cooling. The
cable trays have been extended in the lateral direction however, so the
space in these trays should(??) be suficient. The west side was being pulled
from the platform to the bottom of the cryostat today. The suggestion
after the meeting was that we have two crews working on getting the cables
up the side of the cryostats and into the preamp boxes. We only have
3 sets of extender rods for pulling out preamp boxes, however. We
need to find a way to close the boxes. All these cables need to be
in place by Monday July 19.
Labels have been ordered and should be here next week. L. Bagby
has worked out the labelling scheme.
M. Gao,
H. Fu and G. Uhrhan will help Victor and Kyle on these under the supervision
of P. Liston. M. Tuts will send mail to ensure we get Victor and
Kyle's help next week.