D0 Calorimeter Electronics Upgrade Meeting Minutes
July 30, 1999
present: M. Tuts (MT), P. Liston (PL), L. Bagby (LB),
D. Huffman (DH), G. Uhrhan (GU), H. Fu (HF), D. Elvira (DE), M. Gao (MG),
C. Hays (CH), L. Groer (LG), P. Petroff (PP)
Minute taker: Leslie Groer
= ACTION ITEM
Preamp Fans
GU has located the manufacturer for the
preamp fans. The same size and cooling power (180 cubic feet per
minute) is available but now draws 30W rather than 50W as the old ones
did. (ed. note: later investigation gives cost of $75/unit.
We will try and obtain one to put in the field tests starting Aug 9).
The next size up in fan is probably too big to fit in the box.
Cables
Cabling has been going very well.
All calorimeter preamp pulser cables are in place. (ed. note:
termination was completed and checked over the weekend by PP, Patrick Cornebise
and Bob Olivier.) This is the final note from Pierre Petroff, Aug
2:
Date: Mon, 02 Aug 1999 21:20:37 +0200 (METDST)
From: Pierre Petroff
Subject: Cabling and Fanout
Hi,
1) cabling
The mounting of the connectors is completed (except South End Cap of
course) The ICD cables should be equipped today or tomorrow
A full test has been also performed by using a connector with
different resistors on each channel on one side and by measuring the
resistivity at the other side. This connector is moved from one
cable to one another, owing to check the labelling too.
boxes tested: 00 (ECNNW) 01 (ECNSW) 02 (CCNNW) 03 (CCSSW)
08 (CCSSE) 09 (CCNNE) 10 (ECNSE) 11 (ECNNE)
(boxes 04,05,06,07 are on South End Cap)
Test done by Olivier,Patrick and Pierre
Results: all connectors are ok and labelling ok but one (box 09 bottom A
and bottom B inverted downstairs. This has been fixed)
Thanks to Patrick Cornebise for this nice job !!
2) Fanout
The new fanout redesigned by Christophe will be tested by Gisele in
August and sent as fast as possible to Fermilab for a final approval
before starting production.
The connectors on the card must be on the left side as current cables
arrive by the left (to be checked !).
Some measurement of the magnetic field will be performed on the platform
This concerns the inductance on the switch (already tested at Orsay in
a magnetic field). In the same time a test of the pulser power supply
will be performed.
kind regards
PP
Also see the note
summarizing work done last week from Ursula Bassler from July 28.
ICD cables: (ed. note) Work started on
pulling the 100 ft pulser cables on Monday Aug 2. The platform end
by PW02 have been terminated. The two North EC cables are through
the winder but unterminated - we can get the termination block back in
Nov/Oct if need be. The South EC are pulled up to the winders.
No yellow trigger cables pulled yet for ICD.
Preamp cables
Patrick Cornebise pointed out that some of the
silvered coax cable ribbons from the cryostat feedthroughs to the input
of the preamps are damaged. MT and LG investigated further and in
the two boxes examined 10L and 10R (ECNE) there are 5 (10L) and 1 (10R)
damaged cable/s in the bottom bundles. Some extra strain relief will
be needed to ensure these cables do not suffer further damage rubbing against
the sides of the box but EXTREME CARE NEEDS TO BE EXERCIZED IN OPENING
AND ESPECIALLY CLOSING THE BOXES. The opinion at the moment is that
we will try to splice these cables together due to the extreme intricacy
and inaccessibility in replacing these cables.
All
the boxes need to be examined so we know how many damaged cables there
are and also preventitive steps should be taken to avoid further damage.
MG and SF have put the covers back on the
cable trays that they can get to. The ones on the north side of ECN
need to be put back by Delmar and his crew.
Solenoid Test
The muon iron will start closing up Monday, Aug
9. Current schedule for opening again is first week Sept. At
the solenoid meeting Friday morning there was definite confusion about
whether the preamp platforms can stay in place or not. The muon people
claim that there is no way the hinges can remain according to their design.
The suggestion was to actually measure the pieces to gauge if the hinges
need to come off or not. It was unclear by the end of the solenoid
meeting what the actual plan was.
We would like to have a preamp power supply, a
fan, some preamp boards and some hall probes in the boxes prior to the
iron closing, monitored via a 1553 so that we can log the effects of the
field. Most of the pieces are ready to go in and work will progress
on this next week under DH.
The Columbia office PC will
be used as a second logging machine, assuming we can get the Excel spreadsheet
running - LG will look into this.
Preamp production
KTY has sent back a further request on what they
would like a connector to look like. We think the cut-cut-push and
epoxy connectors will do what they require.
The preamp species D current windows have changed
slightly and need to be signed off . ( ed. note: this was done Monday,
Aug 2).
The revised PO has been shipped to UTY and we
expect the PO from Vista TY any day now. The parts will be shipped
to Vista TY,CA. The material move order forms are ready, and all
the parts are packaged (bar the connectors), ready to go. LG will
look after this next while LB is away if the PO's come through....
The epoxied connector job still not started as
need our go ahead and PO. (ed note: go ahead given Mon, Aug 9).
We might want to requote the preamp motherboard
stuffing job due to the unsatisfactory reponse of Circuitronics to our
requests about their QA. We could send the few preproduction newly
designed motherboards to the new vendor as a test.
The H-series test jigs are almost ready to go
out for quotes and production. DH and PL suggested that the PO process
be started now, to avoid delays. PL will work on this while LB is
away.
MG has finished the layout for the prototype
motherboard production - 6 are being ordered. should be here in a
week or so. They will make sure that the thickness does not exceed
0.62 mils. This has required shortening a few of the inner ground
planes.
SF has been looking at barcodes for the preamps.
She suggests at least 3cm i.e. about 1.5" would be best for the width to
get 8 alphanumeric characters.
Power Supplies
A preamp PS prototype will be put in
box 8R (powering both 8L/R - CCSE) for the solenoid test. The 1553
in place there seems to read out fine. A fan is in and powered. 3-D Hall
probes will be installed. One will be placed outside a preamp box
as well.
Six loaded preamp motherboards will be placed
in 8R to load the power supply.
We'd like to monitor the speed of the fan with
an optical tachometer - MT will order one. There are temp. probes
already mounted and read out via the 1553. The yellow pulser cables
will be used to bring signals downstairs.
There were questions about whether the BLS power
supply can and should be tested in the field. Water needs to be routed
on the platform to do this - not time critical to do this as we have access
to the platform during the working hours during the solenoid test.
PP asked also if the pulser PS could be tested
in the field. There is a fully functional prototype in the 5k test
at the moment which could be used, if we can get it to the BLS racks.
PL working on getting PS parts.
DH - We had a bunch of 3-phase solid state relays of the wrong type
(for a year), which were replaced by the supplier. PS prototype
will be done soon.
SCA's
PL shipped 12 4"-wafers for packaging
with the new "optimized" process. 6"-wafers are on schedule and should
be here 1st week September. Another bunch of 4" SCAs are being burned
in for 2 weeks.
Timing and Control
D. Elvira working on state transitions.
He has a more efficient decoder and demultiplexer. This makes the
design clearer. He is working on the problem of timeing out when
a SCA is not read out for too long. He needs a bunch of counters
for each cell - this is expensive in gates but there are enough in the
L2 FPGA. What they need are more pins - they will spilt the design
into 3 FPGA chipos soon anyway. He does not forsee any major technical
stumbling blocks at the moment.
This page updated 6-August-1999
Send comments/corrections to Leslie Groer groer@fnal.gov