Hi Bob, This is the list of survey tasks remaining for muon. It's a complete list in that I don;t know of anything else. Phase III surveys of the CF toroid and EF toroids would normally be done after every cloing. It is slightly priority ordered. Your friendly neighborhood, Tom PHASE II SURVEYS 96. Survey of 4 N and S EF Top C-Layer PDT's after their installation 1d (ASI) These have to be redone as they are at issue. We suggest also surveying some other nearby chambers, perhaps B-layer tops, in order to provide a constraint. Input from the survey group, as to which additional chambers could provide constraining measurements, would be helpful and appreciated. 15. Survey positions of A-Layer Pixels's once they are mounted 2*1/2d (ASI) 8 Octants per Layer per detector end. Surveyed bottom but not top, both ends. 94. EF N & EF S Bottom B A & B-sides (ASI) 2*1/4 d Chamber Collision with obstacles mandate resurvey. 95. Survey of CF Bottom E + CF Bottom W PDT's 2 days (ASI) 8 PDT's, shooting tooling balls through holes in the floor. PHASE III SURVEYS 100. Resurvey Final positions of EMC N and S (2d) ASI We moved the truss frames after roll-in. This has to be redone. Requires EF irons closed. 98 CF w.r.t. centerbeam. Once the CF's closed Also, need to replace a busted-off tooling ball. 99. EFN and EFS w.r.t centerbeam. Once EF's are closed. 93. Laser Tracker survey of Collision Hall Monuments (ASI) 1d This is easier to do pre-roll in. Done, but awaiting results.