Shutdown 2006 Schedule

When What Who Status
03.Mar.06 Fix preamp power supply. Dean, Julie Done. Fixed by Dean and Jon Fogelsong disconnecting and reconnecting cables at detector end on east side. Overcurrent may have blown fuses, so LED run should be taken ASAP.
Get Rad Worker certified. Neveen Done
Setup tables, storage locker. Pete Simon Tables up.
06.Mar.06 (Fix preamp power supply.) (Julie, Neveen, Norm)
Take LED runs. Neveen, Julie Done.
08.Mar.06 Put test stand together. Mark Sosebee Delayed.
09.Mar.06 Pull drawers from SW quadrant, replace preamps, & bad PMTs, begin testing. Mark Sosebee, Neveen, Julie Delayed.
10.Mar.06 Finish testing SW quadrant, reinstall. Mark Sosebee, Neveen, Julie Delayed.
Test SW quadrant in situ (if DAQ is available). Neveen, Julie Delayed.
13.Mar.06 Put test stand together. Mark Sosebee
14.Mar.06 Pull drawers from SW quadrant, replace preamps, & bad PMTs, begin testing. Mark Sosebee, Neveen, Julie

Julie Kalk