DØ Current Daily Run Plan

The Run Plan can be found at http://www-d0.fnal.gov/runcoor/runplans/runplan.html

The Run Plan Standard Instructions can be found at
http://www-d0.fnal.gov/runcoor/runplans/runplan_standard.html

This run plan covers:

From : Eve shift Jan 02, 2001
Through: Eve shift Jan 03, 2001
Magnet configuration (check magnet orientation instructions in the Standard Plan) :
Toroid: On Forward
Solenoid: On Forward

Current Situation and Plans

Store 875 is colliding. The store will remain until 08:00 Thursday morning with accelerator studies starting at 06:00 or 07:00 and planned to continue until 08:00 Friday. If the beam is lost then studies will start earlier. Shot set up is planned for Friday DAY shift.

The main task of the shift crew is to collect data in stable global runs. Maximum input rate into Level 3 will be dictated by stable running and currently is about 12-15 Hz. By default, all crates should be included in global runs unless experts have removed them, with the exception of the CFT (see below). Experts should be contacted if there are problems with any of the readout crates.

The FPD can move their Roman pots not earlier than 1/2 hour after beginning of store. There is a plan agreed to by Run Coordinator and the Beams Division (see Standard Run Plan). Before any pot motions the MCR and CDF must be informed. In particular, CDF would like to be informed about which pots are being moved.

The major shift tasks are:

Any work that will be disruptive to data taking during colliding beam (e.g. DAQ system tests, L3 tests, TFW work, sDAQ etc.) must be approved by the Run Coordinator.

All work in the MCH must be done with the full knowledge and presence of the experts and can only occur during times when there is no colliding beam. No cables, configurations, crates etc should be changed without the experts' explicit approval. Also the shift captain and DAQ shifter must be kept informed of any activity in the MCH (this includes test systems for L2, STT, etc.) and this work needs to be recorded in the electronic logbook, with the names of the people involved.

CFT Operations

Until further notice, to aid debugging and commissioning the CFT, the following plan is in effect. When there is no colliding beam, the CFT crates are under the control of the CFT shifter.

During colliding beam:

  1. The CFT shifter will communicate with the Captain and DAQ shifter and request whether the CFT crates (0x50,0x51,0x52,0x53) are to be included in the primary global run or not.
  2. If desired by the CFT shifter, CFT crate(s) will be excluded from the global run and sDAQ runs with the CFT only may be run independently.
  3. If independent CFT pDAQ runs or unsuppressed CFT running in the global runs are requested, the Run Coordinator must approve the run. This does not apply to sDAQ runs.
  4. Once debugging work with one or more CFT crates has been completed and the crates are available for more than an hour for regular running, the CFT shifter should inform the Captain and DAQ shifter that the crate(s) are available for global runs. These crates must be run in suppressed mode. The global run should not be stopped just to include these crates, but the next natural, convenient break in the run should be used to include the crates.

Standard Trigger Files

For colliding beam trigger configuration file is

global_CalMuon-3.10.xml

There are prescale files for 1, 2, 4, 6, 8, 10E30 and a panic file. For example, for luminosity between 3E30 and 5E30 use prescale file 4E30 and similar for other prescale files. If there are problems with the v3.10 file, contact the Trigger Meisters.

For cosmic ray running use one of two files (depending upon L2 crates status):

cosmics-1.1.xml - does not include the L2 crates
cosmics-1.2.xml - contains the L2 crates in non-readout mode
For proton-only beam running:
proton_halo_only-1.2.xml

Planned Special Runs or Activities

Special DAQ stability and rate test to be conducted during OWL shift:
Use prescale sets 0.5x and 1.5x nominal rate (e.g. for 4E30 use 2E30 and 4E30) during stable DAQ running. Take date for about 20 minutes taking special note of livetime/deadtime and DAQ stability. The conditions between the two runs should not be changed (e.g. number of crates, thresholds etc.). The goal is to achieve about 10-12 Hz with the lower prescale set followed by one with 5-6 Hz. Return to regular running at the conclusion of the tests.

See the Special Run Request Binder for details
Special run forms are available in the Special Run Requests binder in the control room.


Send comments/corrections to Leslie Groer
Last modified: Tue Oct 22 05:33:19 CDT 2002