The default running condition for a store - unless otherwise specified and
approved by the Run Coordinator - is to run with all available readout crates
in the global run with Recording On. Please review the
D0 Run Plan
for current plans and situations.
Shift Captains are responsible for enforcing the Run Plan
and resolving conflicts.
Work that influences or impacts the DAQ between stores must be
scheduled in advance and approved by the Run Coordinator.
See the sections on CFT Operations &
CFT to L1 Muon Commissioning &
Combined Test Stand Operations &
STT Operations for special instructions.
|
|
To assist in the commissioning the CFT+PS, the following plan is in effect
until further notice. When there is no colliding beam, the CFT crates are under the
control of the CFT shifter.
During colliding beam:
The CFT shifter will communicate with the Shift Captain and DAQ shifter
whether or not the CFT crates (0x50,0x51,0x52,0x53) should be included
in the primary global run. Removal of CFT crates from the
global run for reasons other then fixing immediate hardware or software
problems must be approved by George Ginther or Andrew Alton. Unless
explicitly approved, the default condition is to leave the crates in the
global run (running in suppressed mode).
The CFT crate(s) can be excluded from the
global run and CFT-only sDAQ runs may be run independently.
If independent CFT pDAQ runs or unsuppressed CFT running in the global
runs are requested, the Run Coordinator must approve the run. This
does not apply to sDAQ runs.
|
STT Operations
last updated 30 October 2002
The STT crates x70, x71, x72, x73, x74, and x75 are now part of the
Crater GUI. These crates are in "NO-VBD Mode". Readout to Level 3 is not
enabled in the STT crates, and L3 does not expect them to be in the
readout. Moreover, the parallel cables back to the trigger Hub are not connected
for these crates, meaning they cannot cause any busies or errors.
Even if the crates are powered down or in some kind of error state, they
*cannot* have any impact on the global run. To support STT commissioning,
crates x70 and x73 should always be part of the global run to provide trigger
information. Other crates may be added upon request.
The STT group might request special runs between stores to exercise the
STT system at higher L1 accept rates. These will be global runs with only
a few crates in the run to reduce front end busy rates.
In case of questions, please call Georg Steinbrueck x4348 or Bill Lee
x2490.
These procedures will be reviewed and/or changed when an SBC is added
to the STT crate so that data is sent to L3.
|
|
The Shift Captain is responsible for providing the D0 Ops Shifter with
instructions on turning the D0 magnets ON/OFF or changing the polarities.
The solenoid takes about 20 minutes to discharge and the toroid about 10 minutes.
The shift captain should verify with the Ops Shifter that the magnet power supplies
are interlocked after being ramped down.
Before the solenoid or toroid are turned on or off, MCR must be notified.
Any changes in magnet currents should occur when there is no
store in the Tevatron. The MCR should be notified by the Shift
Captain at least 10 minutes before any changes to the D0 magnet operating
conditions.
The polarity of the magnets is to be changed every week. Changes are to
be done before the first store that starts after the beams studies period that
normally occurs on Tuesday and Wednesday of each week, and
will be done independent of the amount of data collected during previous
week(s) or any other conditions.
Future polarity sequences (R - Reverse, F - Forward):
| Week of |
10/8 |
10/15 |
10/22 |
10/29 |
11/5 |
11/12 |
11/19 |
11/26 |
12/3 |
12/10 |
| Solenoid |
F |
R |
R |
R |
F |
F |
R |
F |
F |
R |
| Toroid |
F |
F |
R |
F |
F |
R |
R |
R |
F |
F |
Special modes of operation for the magnets (no field for detector
studies, etc.) will be described on a case by case basis in the run
plan. As soon as such studies are over, we should return to the sequence
outlined above.
In order to reduce operating expenses, the solenoid and toroids should be
powered OFF if it is known that collisions are not expected within the next
24 hours. They should be turned ON at least 1 hour before the expected
shot setup.
During magnet current changes, follow the procedures outlined in the run
plan for operating the
luminosity counters' high voltage.
No other detectors are known to be affected by the magnetic field changes.
|
Shift Captains are responsible for communicating to all detector
shifters about the beginning of a store. The
Shift Captain should specifically instruct the Muon & SMT detector shifters
to set their HV to 100%. Data taking should be started after HV is at 100% for
all detectors in trigger/readout.
The MCR should call D0 about planned store terminations. Near the end of a store,
the Shift Captain will instruct the DAQ Shifter to end global data taking, followed
by asking the Muon and SMT detector shifters to set their detector HV to "Standby".
To avoid confusion, refer to the table below for which systems need to regulate their
HV depending on beam conditions.
The Luminosity HV stays ON at all times, even during
beam studies, but the setting of the HV to lower or higher percentages
depends on the solenoidal field being off or on.
| | Beam conditions |
|---|
| Detector | Shifter |
Collisions | Injection |
Beam studies | No Beam (Calibrations) |
| SMT | SMT shifter |
100% |
OFF |
OFF |
100% |
| CAL | CAL shifter |
100% at all times |
| ICD | CAL shifter |
100% at all times |
| MUON | MUON shifter |
100% |
Standby |
Standby |
Standby |
| LUM | Captain |
70% at all times with solenoid off 100%
at all times with solenoid on |
|
|
For more details and default positions, read the
FPD Run Plan.
The D0 Roman pots move to standard positions for most stores
not earlier than one half hour after the beginning of the store.
The Shift Captain must notify MCR before any pot is moved.
CDF has asked to be notified about which pots are being moved so they
can correlate the motion with their losses. The pots will remain at these
positions for most of the store. The pots are retracted prior to the
beam being aborted or machine studies. An FPD Expert will be present
for all pot insertion.
The D0 FPD information is contained on ACNET page C72.
- Subpage 1 shows if the home limit switch is set. When the system is in
standby, these should all be 1.
- Subpage 2 shows the Linear Variable Differential Transformer (LVDT)
values. When the system is in standby, these
should all be fluctuating around 0. As the pots are inserted, the
fluctuations become small allowing precision of at least 0.1mm.
- Subpage 4 shows the single counting rates for each pot that is
instrumented with a trigger PMT. It also shows the losses for D0 and CDF
at the bottom.
The D0 Roman pot operating positions are determined by one of two things, whichever
occurs first. If the singles rate at a location increases much beyond
100kHz we stop there. Otherwise, we only insert until the first
indication of increased losses at CDF or a 10% increase in losses at D0
(cumulative for all inserted pots).
The Shift Captain can monitor D0 losses at C:D0PHTL and C:D0AHTL.
A-side pots affect p-halo and P-side pots affect a-halo. (Dipole pots
don't affect halo up to nominal positions).
CDF will be moving their forward proton pots at the end of some stores.
CDF should inform D0 before they start. CDF has a similar ACNET page at S4
subpage 4. In the middle of the page, the three readouts of the Tokyo Pot
LVDTs is displayed (C:TPOT1M, C:TPOT2M, C:TPOT3M). Normal CDF LVDT readings when
CDF pots inserted are approximately ~-871mils for pot1, -901mils for pot2
and -854mils for pot3. The Shift Captain should watch D0 losses during the
motion of CDF pots.
|
Full details on
FPD Procedures for CAL Shifters and
Emergency Pot Removal.
FPD Expert pager numbers are posted at the FPD & CAL consoles.
To assist in the 24/7 operations of the Forward Proton Detector & collection of
the FPD standalone data, the Calorimeter Shifters are trained and have been approved
to perform many of the FPD tasks when an FPD Expert is not in the control room.
There will be an FPD Expert on-call for day (08:00-20:00) and night (20:00-08:00) shifts
to help in inserting pots and resolving any problems.
The FPD Expert will insert the pots (pot insertion will only occur between
08:00-24:00) and verify that everything is in working condition (FPDGui, DAQ, HV, alarms).
The FPD Expert will:
- Gather the pedestal file and set up the FPD DAQ to run properly
- Determine the next run number to be used and pass this information on to the Calorimeter shifter
- Record initial conditions in the e-log book
- Review these instructions with the new Calorimeter shifter as they switch over
The Calorimeter Shifter tasks are:
- To collect data and monitor rates
- Watch for fire alarms (none have ever happened)
- Putting the FPD system into standby (removing pots, putting HV into standby, turning off control lines)
when the Shift Captain give notice of the end of store, of if then store ends unexpectedly (for example, quench)
If the computer stops responding to the mouse or the FPDGui becomes unresponsive
contact the FPD Expert to bring back up the system. If you have to remove pots while the system
is in an unresponsive state, then use the Emergency line to remove the pots. Verify the pots are
at home in the C72 window (window 3 of ACNET display). Click in the upper right corner where you
see -<4>+ on the - until you see -<1>+. On this page all of the pots should show a value of 1 if they are home.
If you click on the + you will go to -<2>+ where you should see values hovering around 0.
When the pots are home, turn the Emergency Line off. To put the FPD HV on standby, open an xterm
from the Calorimeter console, and then do the the following:
- Type setup d0online
- Type /online/config/fpd/hv/fpd.hv &
- Follow normal instruction for putting HV into standby
- Close the HV Gui by clicking on File then Exit
The Shift Captain and Calorimeter Shifter must make sure the FPD system is in standby before the store ends.
If anything happens that is not covered in these instructions, contact the on-call FPD Expert at any time.
IF IN DOUBT, TAKE THE POTS OUT.
|
Luminosity
last updated 24 October 2002
During magnet current changes, follow the procedures outlined in the Run
Plan for operating the
luminosity counters' high voltage.
No other detectors are known to be affected by the magnetic field changes.
How to tell if the Luminosity information is updating in ACNET
Comments on the lmCaptain/lmShifter GUIs:
- lmOnline acquires information from COOR and DataLogger. The COOR
record should only update when there is an end run; the DL record
should update whenever a new partition is written to disk.
If there is no recorded activity, then the lmOnline keys can become
very late. That is one reason why they never turn red in the GUI.
|
Controlled accesses are often made available during unscheduled
Tevatron down time - quench, power glitch, vaccum failure - which could happen 24/7.
It requires significant coordination and cooperation between MCR and D0, and
between the Run Coordinator, Shift Captain, Controlled Access Coordinator and
Detector Experts. A maximum of eight people are allowed
inside the D0 Collision Hall at one time during a controlled access. Each
access is restricted to a maximum of four hours, although most are less than
an hour. In order to take full advantage of an access
opportunity, we need to be prepared and organized. If you have a job that can
be done during a Controlled Access, then send email to the
D0 Run Coordinator with:
- a brief description of job,
- the level of urgency,
- the amount of time needed to complete the job, and
- the persons who will perform the job.
With approval from the Run Coordinator, make a note on the Controlled
Access whiteboard in the D0 Control Room, with your contact info & availability.
Approved Controlled Access Jobs can also be found from the Run Plan.
The Shift Captain should contact the MCR at the beginning of each shift, and
as needed, to keep up with the dynamic schedule of the accelerator. D0 may be
able to take advantage of unscheduled downtime to make a controlled access.
Contact Dmitri Denisov, the D0 Run Coordinator
for approval if there is an access opportunity.
The list of Controlled Access Coordinators with their contact information is in the
General Personnel Call Lists binder.
Your training must be current in order to enter the collision hall
during accesses. See the section on Training for more details.
Contact Bill Freeman or the
D0 Run Coordinator
if there are problems.
Film badges and hard hats must be worn in the
collision hall. A rate meter is also required for each location.
Sandals and open-toe shoes are not appropriate footwear
because of saftey concerns. Leather gloves and safety glasses may be
required for some jobs.
Controlled Accesses - which we need in order to make periodic repairs
and upgrades to our detector - are a privilege, not a right, extended to D0 by the Beams
Division. Please be prepared, attentive and safe!
|
Training
last updated 23 August 2002
All shifters are required to have D0 Hazard Awareness Training
[valid for 2 years] and
Lock-Out Tag-Out (LOTO) I Training
[valid for 100 years].
Verify your training at the ES&H
Training Plans page
[FNAL domain].
Enter your ID (employee or visitor) and select ITH (Individual Training History)
under Option 1. The Due Date shows when your training will expire or has expired.
To renew your training, simply enroll yourself in a class or challenge exam session
which are usually offered weekly.
D0 Hazard Awareness handouts & quizzes are available on the web (in PDF).
Copies are in the control room as well in the rack near the MCH1 door. Keep the handout,
but return the quiz and the form on the last page to the appropriate slot in the rack.
Send email to Bill Freeman to arrange LOTO I training.
Access to the D0 collision hall will either be Supervised or Controlled.
To make any access, Radiological Worker Training
[valid for 2 years] is required.
Additional training - Fermilab Controlled Access Training
[valid for 1 year] -
is required in order to make a controlled access. It is strongly recommended
that shifters get Rad Worker and Controlled Access training, and keep current,
so D0 can take full advantage of all opportunites to access the detector for
repairs, maintenance and upgrades.
|
TLD Badges
last updated 3 August 2002
Please read the Information for
Temporary Badge Holders document (copies are also available in the control room), before asking
the Shift Captain or Controlled Access Coordinator for a temporary TLD
(thermoluminescent dosimeter)
badge - they are the only ones authorized to distribute the temporary
TLD badges!. The badge is attached to
a card. Fill out the card completely, and deposit it in box next to
the first floor Moveable Counting House (MCH1) door. Each Temporary TLD
badge (red plastic) has a unique badge number
which is associated to a specific user from the temporary badge card.
Temporary TLD badges should be dropped in the box when:
- the user has completed the one time access to the D0 Collision Hall, or
- the user will not be entering a Radiation Area in the near future, or
- the 3 month period (quarter) has ended.
Temporary TLD badges & forms as well as Permanent forms will be collected
weekly and shipped to Dosimetry at MS119.
If you will be at D0 for an extended period of time, and expect to enter
Radiation Areas such as the D0 Collision Hall, you should fill out the permanent TLD badge
form in the control room and leave the completed
form in the boxk near the MCH1 door.
Or, one can print the
Permanent Badge Service Request Form from the web, and send to Dosimetry at MS119.
The permanent badges (black plastic) are stored on racks near the DAB1
elevators. Every three months, the permanent badges are collected for
testing and replaced with a new one. You will receive an email reminder at the
end of each quarter to return your badge to the rack.
Please do not take your TLD badge off-site. The TLD badges (permanent and temporary)
are used to measure the radiation exposure you receive while in
Radiation Areas at Fermilab. It is a good habit to leave your TLD badge on
the racks next to the elevator before you
leave DAB1.
|
Power Outages
last updated 11 August 2002
In the event of an unscheduled power outage or interruption, please follow these
procedures:
- DAQ, Ops and detector shifters have instructions on how to bring their
systems back after a power outage. The Shift Captain should monitor their progress and
help with the paging or calling of appropriate experts.
- Groups which want their on-call experts paged by the Shift Captain are:
- Luminosity
- L1 Muon
- FPD
- L2
- Online (Stu Fuess)
- Rich Smith/Lukas Phaf - restart the Hall monitors for the D0
solenoid
- Run Coordinator should be paged as well
- Other experts should to be paged or called in the case of problems only
|
SMT Voltage
last updated 13 August 2002
The SMT system is the only sub-detector in which damage can
occur from high voltage (HV) being ON during beam losses. In the
Calorimeter, ICD, Muon and Luminosity systesm - while the
HV channels could trip - this will NOT damage the detectors.
The SMT shifter should not leave the control room for long periods of
time (>10 minutes) while even the LV is up, especially not
when the HV is up, unless there is another SMT shifter or expert
to relieve him/her.
The Shift Captain MUST check with the SMT shifter that the SMT HV
(and low voltage) is OFF before excusing him/her from the control room
shift. The SMT shifter must also contact the SMT On-Call expert before
leaving.
We require Shift Captains to be around during all shifts with
beam (even if there are no collisions) due to a single reason - SMT radiation
protection.
|
|
The CFT+PS shifters and experts are allowed the opportunity to attempt
to incorporate the L1 CTT crate x13 into the global run at any point between
stores - even up to scraping. If the crate is made to run during that time
period, then it will be allowed to remain in the global run. If the crate
goes FEB, then the shifters will attempt a few well-defined steps that
have been mapped out and tested between stores to attempt recovery. Proceed
to the second step if the first step is unsuccessful:
- Pause, re-download crate x13 and resume
- Pause, re-download crates x50 and x52, then resume
If crate x13 fails to behave after these steps have been taken, then
it should be removed from the global run and left out until the experts
have a chance to try to get it going again between stores.
|
The Combined Test Stand (CTS) resides on the third floor of DAB, and is used
to test AFEs, sequencers, sequencer controllers and the CTT.
The CTS runs can continue to be performed as SDAQ runs on an as needed basis.
The person operating the CTS is required to keep the CFT+PS Shifter informed of CTS
activities and the DAQ Shifter of CTS runs.
The CTS runs should have prescales set to provide L1 trigger rates of less
than 50 Hz. If higher trigger rates are required, such studies should be performed
between stores, and only after notifying the Shift Captain and DAQ Shifter.
Sometimes, crate x9 shows up at the DAQ Console as 100% L1 FEB, but this has
no impact on the data taking, and can be ignored.
|
Prescales
last updated 30 October 2002
There are many factors which affect the optimization of prescale sets for
global running: trigger and DAQ rate capabilities, off-line farm
production status, physics goals of the experiment, etc. Trigger Meisters with
guidance from Trigger Board are creating/optimizing prescale sets.
For trigger version 9.20 we currently have prescale sets with ~20% steps in
luminosity.
The selection rule for choosing a prescale file is rather simple: at the
beginning of the global run select the prescale file with the name closest to
the current D0 luminosity. Run with such prescales for a maximum of 4
hours or 500,000 events unless major hardware/software problems
which affects run quality occur.
Keep in mind we are running all critical high pt triggers un-prescaled.
Changing prescale files will not increase data sample, rather reduce
it due to time lost ending/beginning runs.
For global runs, the rate to tape is not a measure of the D0 efficiency.
It could be that we are limited by L1 or L2 rates, rather then rate to
tape. It is the Trigger Meisters who optimize all rates. In the case of
serious problems with some of the rates you should page Trigger Meisters,
rather then try to modify prescales or use higher/lower prescale files.
They will help you to resolve problems, if any, or will make long term
changes in the prescale files.
As of now typical ranges for the rates during global runs are (all rates
are in Hz):
L1: 200-400 L2: 100-200 L3: 30-60
|
Rick Hance and Mike Cherry have prepared a safety document which details the
Procedures for Changing a Calorimeter BLS Power Supply.
This procedure is for those times when Electrical/Electronics Operations
personnel are not available - such as at short controlled accesses during off-hours.
The urgency of replacing a BLS power supply will be determined by Nirmalya
Parua (or by the Calorimeter Expert on-call when Nirmalya is away).
Spare power supplies are located at the NE and SW corners of the D0 Collision Hall.
The procedure requires two physically fit, strong and healthy helpers
to maneuver the heavy (50 kg) power supplies. One of the helpers should
always be the Operations Tech on duty who is familar with the process.
Nirmalya has provided a
List of Qualified Helpers. The qualified helpers must wear
leather gloves and steel-toed shoes during the maneuvering of the
BLS power supply. The person(s) handling the water hoses must wear
safety glasses.
If the bad BLS supply is on the north or south central platform, first notify the SMT shifter
or expert to turn off their supplies (IB and sequencer). This is a preventative measure to
protect against accidental power trips due to water leak detection.
Tools required: Flashlight; Phillips & Standard screwdriver; two disconnect fitting
plugs for water hoses; bucket & box of Kimwipes.
|
|
To assist in the commissioning the CFT + L1 Muon trigger, the following plan is in effect
during colliding beam, until further notice:
The L1 Muon expert (Rob McCroskey, Ken Johns, Jeff Temple or Stefan Anderson) will:
- Request a run pause
- Enable the CFT sectors of interest
- Request an SCL init
- Verify all rates are OK
- Request the run to be resumed
The total time should take less than one minute. The
CFT inputs will remain enabled until the L1 Muon expert is done with running.
Then the process is repeated:
- Request a run pause
- Disable the CFT sectors of interest
- Request an SCL init
- Verify all rates are OK
- Request the run to be resumed
In the case where something goes wrong, the system is returned to the default configuration
with no CFT inputs enabled to L1 Muon, and the L1 Muon expert will study the problem between stores.
|
To assist in the commissioning the L1 Muon trigger, the following plan is in effect
during colliding beam, until further notice:
From time to time, the L1 Muon team (Rob McCroskey, Ken Johns, Jeff Temple
or Stefan Anderson) will have new logic for their trigger manager which is designed
to add new terms for triggering. They can check most of the terms with no beam,
but they need to do a final check during a store.
This work will be performed at the end of the store. When new logic is ready,
the L1 Muon Expert will request a page from the Shift Captain about 1-2 hours before
the scheduled termination of a store. The logic change should be performed in
the last hour of the store. The total time to change logic and record rates
is about 10 minutes. If there is a problem with the new logic, it takes about 10
minutes to change back to the old logic.
|
|
There will be periods, particularly on owl shifts with no beam or chance
of beam, when the Calorimeter Shifter is on-call and not in the Control Room.
By default the Calorimeter crates are left in the global zero-bias run,
but on occasion one of the CAL crates (x40-x4b) will assert 100% L1 FEB,
such that data taking has stopped.
Solution:
- DAQ Shifter should pause the run
- Go to the CAL console, screen 2 (on right), Supply GUI, Mode Shift tab
- Click on 'Global T&C Reset'
- Click on 'Global ADC Reset'
- Click on 'Global T&C Reset' again
- DAQ Shifter should issue an SCLinit
- DAQ Shifter should resume run
If for some reason the 'Supply GUI' is not open, you can do:
setup d0online
/online/config/cal/supplies/supply_all &
in order to complete Step 2 above.
|
|
|
|
|
|