DØ Trigger Upgrade Workshop, 11-12 Oct, 2003

 

Link to list of registered participants

 

Draft goals:

  • Share technical experience
  • Evaluate project status
  • Identify what remains to be done
  • Plan how to get the work done
  • Bring new/interested people up to speed on what is going on
  • Develop an improved straw-man trigger list for 2006

 

Special scheduling considerations:

  • L1cal integration tests are going on concurrently, so we want to limit and concentrate the technical L1cal discussions so that the critical people can leave the workshop and work on the integration tests

 

Final agenda:

 

 

Curia II

Breakout room (Commitium)

Saturday, Oct 11th

9:00

Workshop goals: Paul & Darien

Upgrade project status & review process: Vivian O’Dell

 

 

 

9:30

L1cal overview: Hal Evans

 

10:00

Parallel session: L1cal discussion

Parallel session: CTT algorithms

 

11:00

L1 Cal-track overview: Ken Johns

L1cal & cal-track discussion

CTT parallel session, algorithms

12:00

Lunch

Lunch

1:00

Status: CTT hardware: Meenakshi Narain

Status: CTT algorithms/equations: Mike Hildreth

 

2:00 – 4:30

Parallel session: L1cal controls and monitoring

Parallel session: CTT hardware

7:00

Banquet – Cuisine of India, Naperville

 

Sunday, Oct 12th

9:00

Timing of trigger upgrade installation: discussion

 

10:00

Trigger lists

Top triggers, current and future concerns/strategies: Brigitte Vachon

 

 

11:00

Trigger list/trigger strategy discussion (cont.)

 

12:30

Lunch

 

1:30

Summary: conclusions & action items from workshop: Paul & Darien

Concluding discussion

 

3:00

End of workshop